There are two classifications of costs associated with construction projects, direct costs and indirect costs. Direct costs include the labor, material and equipment operating costs necessary to put work in place. Indirect costs include supervision, job and home office overhead, profit, financing, and the cost of inflation. Direct costs can be allocated to each activity on the project. Indirect costs, on the other hand, cannot be realistically prorated and assigned to each separate activity.
Case study shows the all activities on performed on construction work. In this study we select an analysis on time cost minimization of construction of sewage treatment plant which is held in shivpuri under national lake conservation project. There are three option of each activity that performed in construction work. First option of each activity is based on work actually …show more content…
work B A 1 0 0 16 0 0 1 2 0 0 0 0 0 35 0 1050000 2 0 0 30 0 0 2 4 0 0 0 0 0 20 0 1042500 3 0 0 10 0 1 0 2 1 0 0 0 0 16 0 1027500
3 steel work C B 1 0 0 7 0 0 0 0 0 3 1 0 0 120 0 11880000 2 0 0 10 0 0 0 0 0 5 1 0 0 100 0 13500000 3 0 0 8 0 0 0 0 0 4 1 0 0 110 0 12960000
4 shuttering D B,C 1 0 0 12 0 0 0 0 0 0 0 5 0 120 5 2790000 2 0 0 15 0 0 0 0 0 0 0 6 0 100 0 2700000 3 0 0 8 0 0 0 0 0 0 0 3 0 140 0 2835000
5 concrete casting E D 1 0 0 16 0 1 0 2 0 0 0 0 0 120 0 16784000 2 0 0 20 0 2 0 3 0 0 0 0 0 100 0 17236000 3 0 0 8 0 1 0 2 1 0 0 0 0 90 0 18240000
6 painting F E 1 0 0 3 0 0 0 0 0 0 0 0 4 15 0 585000 2 0 0 2 0 0 0 0 0 0 0 0 3 22 0 594000 3 0 0 5 0 0 0 0 0 0 0 0 5 17 0 630000
7 water proffing and testing (Epoxy) G F 1 0 0 2 0 0 0 0 0 0 0 0 2 20 0 1824000 2 0 0 3 0 0 0 0 0 0 0 0 4 12 0 1860000 3 0 0 3 0 0 0 0 0 0 0 0 3 16 0