1. Unofficially temporary certification of occupancy (TCO) will be pushed back to the first week of January 2018. We are still waiting for the official announcement.
2. Front turnstile will be installed with no issues.
3. Convergint needs to work with design and the architect to revise the 4 additional turnstiles into the life safely drawings. I believe 2 of the 4 turnstiles locations may be an issue. (The turnstile by audience load in and by the security office.) This would have to be submitted after TCO and completed before a certificate of occupancy (CO). The time between TCO and CO would still need to be approved by the County if the life safety drawings can be revised.
4. There is no