Collect Requirements
|
Inputs:
1 Project Charter, 2 Stakeholder register; Tools & Techniques: 1 Interviews, 2 Focus groups, 3 Facilitated workshops, 4 Group creativity techniques, 5 Group decision making techniques, 6 Questionnaires and surveys, 7 Observations, 8 Prototypes; Outputs: 1 Requirements documentation, 2 Requirements management plan, 3 Requirements traceability matrix. |
|
Define Scope
|
Inputs:
1 Project charter, 2 Requirements documentation, 3 Organizational process assets; Tools & Techniques: 1 Expert judgment, 2 Product analysis, 3 Alternative identification, 4 Facilitated workshops; Outputs: 1 Project scope statement, 2 Project document updates. |
|
Create WBS
|
Inputs:
1 Project scope statement, 2 Requirements documentation, 3 Organizational process assets; Tools & Techniques: 1 Decomposition; Outputs: 1 WBS, 2 WBS dictionary, 3 Scope baseline, 4 Project document updates. |
|
Verify Scope
|
Inputs:
1 Project management plan, 2 Requirements documentation, 3 Requirements traceability matrix, 4 Validated deliverables; Tools & Techniques: 1 Inspection; Outputs: 1 Accepted deliverables, 2 Change requests, 3 Project document updates. |
|
Control Scope
|
Inputs:
1 Project mangement plan, 2 Work performance information, 3 Requirements documentation, 4 Requirements traceability matrix, 5 Organizational process assets; Tools & Techniques: 1 Variance analysis; Outputs: 1 Work performance measurements, 2 Organizational process assets updates, 3 Change requests, 4 Project management plan updates, 5 Project document updates. |