What is schedule variance? SV
|
Earned value minus the planned value
|
|
What is schedule performance index? SPI
|
The ratio of earned value to planned value; can be used to estimate the projected time to complete a project
|
|
What is cost of performance index? CPI
|
Ration of earned value to actual cost; can be used to estimate the projected cost to complete the project
|
|
What is Cost Variance? CV
|
Earned value minus the actual cost
|