- Shuffle
Toggle OnToggle Off
- Alphabetize
Toggle OnToggle Off
- Front First
Toggle OnToggle Off
- Both Sides
Toggle OnToggle Off
Front
How to study your flashcards.
Right/Left arrow keys: Navigate between flashcards.right arrow keyleft arrow key
Up/Down arrow keys: Flip the card between the front and back.down keyup key
H key: Show hint (3rd side).h key
![]()
PLAY BUTTON
![]()
PLAY BUTTON
![]()
23 Cards in this Set
- Front
- Back
|
Agreement:
|
represents and reflects the legal contract between two parties.
This can be between the owner and the contractor or between the owner and the designer or between the general contractor (GC) and the subcontractors or between the contractors and material suppliers. |
|
General Conditions
|
General conditions define the responsibilities of the parties involved in the
contract-the owner and the general contractor. |
|
Special Conditions (or Supplementary Conditions):
|
Special conditions provide an extension of the general provisions of the contract to
fit the specific project at hand. |
|
Addenda:
|
formal
document changes the original bid documents and becomes a part of the bid package. |
|
AIA Document A201:
|
The most common General Conditions used in the construction industry
|
|
Bid Bond:
|
A bond that assures that the contractor will accept the contract when awarded and
will supply the required performance and payment bonds. |
|
Payment Bond:
|
A bond that guarantees that the contractor will pay the subcontractors and material
suppliers. |
|
Performance Bond:
|
A bond that guarantees that the contractor will perform the work in accordance
with the plans and specifications. |
|
Lump Sum Contracts:
|
Lump sum contracts are typically used for structures such as buildings that permit
the bidders to estimate the quantities and costs accurately. |
|
Unit Price Contracts:
|
Unit-price contracts are used for work where it is not possible to calculate the exact
quantity of materials that will be required. Unit-price contracts are commonly used for heavy/highway work. |
|
Cost Plus Contracts
|
Cost plus (cost reimbursable) contracts are used in situations that make it difficult
or impossible for either the owner or the contractor to predict their costs during the negotiation, bid, and award process. |
|
Incentive Contracts:
|
The most common types of incentive contracts are those that offer a bonus for
early completion. Contracts that require a penalty for late completion are required by law to also offer a bonus for early finish. |
|
Job Order Contracts:
|
Contracts used mainly for maintenance work. designed to avoid a design contract for each work order.
|
|
Liquidated Damage
|
Liquidated damages are the money paid by the contractor to the owner if the
contractor exceeds the allowed contract time period. |
|
Notice To Proceed
|
The document that establishes the contractor's right to have access to the owner's
property. It establishes the official start date of the contract, |
|
Substantial Completion
|
The facility must be ready for the owner
to move into and use. |
|
Final Inspection
|
owner's last formal
opportunity to walk through the facility to identify remaining work items and to formally accept ownership of the facility. |
|
Punch List
|
items the
contractor needs to correct to reach final completion, and those items can be completed while the owner is occupying the facility. |
|
Retainage:
|
owner, in order to have protection that the contractor will complete the
work, often holds back (retains) a portion of what a contractor earns until the end of the project. |
|
Progress Payments
|
The actual process of submitting the
monthly pay estimate involves estimating the percentage of completion of each job activity, calculating the amount due for each of those activities, and subtracting the retainage from the total |
|
Worker's Compensation Insurance
|
Workers' compensation protects workers who are injured on the job by covering
medical and hospitalization expenses, plus a percentage |
|
Submittals
|
Submittals contain information concerning products to be incorporated in a
construction project |
|
Claims
|
result of change orders that cannot be resolved or job
conditions that the contractor considers to be a materially changed condition but the owner does not agree. |