PV
Planned Value
EV
Earned Value
AC
Actual Cost
BAC
Budget at Completion
CV
Cost Variance = (EV - AC)
SV
Schedule Variance = (EV - PV)
CPI
CPI = (EV/AC)
SPI
Schedule Performance Index = (EV/PV)
EAC
Estimate at Completion = (BAC/CPI)
ETC
Estimate to Complete = (EAC - AC)
VAC
Variance at Completion = (BAC - EAC)