16 Cards in this Set

  • Front
  • Back
Planned Value (a.k.a. what)
Budgeted cost for the work scheduled to be completed on an activity or a work breakdown structure component. also referred to as the Budgeted Cost of Work Scheduled (BCWS)
Budget At Completion
Sum of all the budget values established for work to be performed on a project; total planned value for the project
Earned Value (a.k.a. what?)
Also referred to as the
Budgeted Cost of Work Performed (BCWP).

Budgeted amount for the work actually completed on the schedule activity or a work breakdown structure component.

Formula: EV = BAC * %Comp
Actual Cost (a.k.a. what?)
Also referred to as the Actual Cost of Work Performed (ACWP). Total cost of accomplishing the work on a schedule activity or a work breakdown structure component
Cost Variance
A measure of cost performance on a project

Formula: CV = EV - AC
Schedule Variance
A measure of schedule performance on a project

Formula: SV = EV - PV
Cost Variance %
Tells you what percentage cost varies for the work performed to date

Formula: CV % = CV / EV
Schedule Variance %
Tells you what percentage schedule varies from what had been planned to date

Formula: SV % = SV / PV
Cost Performance Index
A measure of cost efficiency on a project

Formula: CPI = EV / AC
Schedule Performance Index
A measure of schedule efficiency on a project

Formula: SPI = EV / PV
To-Complete Performance Index
Denotes, from a point in time, the efficiency that must be achieved in order to complete the remaining work with the expected remaining
money

Formula: TCPI = (BAC – EV) /
(BAC – AC)
Percent Complete
An estimate, expressed as a percent, of the amount of work that has been completed on an activity or a work breakdown structure component

Formula: % Comp = EV / BAC
Percent Spent
An estimate, expressed as a percent, of the money that has been spent

Formula: % Spent = AC / BAC
Estimate At Completion
Expected total cost of a schedule activity, a work breakdown structure component, or the project

Formulas: EAC = BAC / CPI
or EAC = AC / % Comp
Estimate To Complete
Expected cost needed to complete all the remaining work for a schedule activity, work breakdown structure component, or the project

Formula: ETC = EAC - AC or ETC
= (BAC - EV) / CPI
Variance At Completion
Difference between the total budget assigned to a project, budget at completion (BAC), and the total cost estimate at completion (EAC)

Formula: VAC = BAC - EAC