Front

How to study your flashcards.

Right/Left arrow keys: Navigate between flashcards.right arrow keyleft arrow key

Up/Down arrow keys: Flip the card between the front and back.down keyup key

H key: Show hint (3rd side).h key

image

PLAY BUTTON

image

PLAY BUTTON

image

Progress

1/18

Click to flip

18 Cards in this Set

  • Front
  • Back
What comes before:

Create Network Diagram
Create Activity List
What comes before:

Prepare Procurement Documents
Determine what to purchase
What comes before:

Create Project Scope Statement
Determine how you will do planning
What comes before:

Create WBS and WBS dictionary
Determine Team
What comes before:

Determine Critical Path
Estimate Time and Cost
What comes before:

Estimate Time and Cost
Estimate Resource Requirements
What comes before:

Develop Budget
Develop Schedule
What comes before:

Gain formal approval
Develop Final PM Plan & Performance Measurement Baselines
What comes before:

Hold Kickoff Meeting
Gain Formal Approval of PM Plan
What comes before:

Determine Quality Standards, Processes and Metrics
Develop Budget
What comes before:

Determine what to purchase
Goback-Iterations
What comes before:

Determine Communications Requirements
Determine roles and responsibilities
What comes before:

Iterations
Risk Identification, Quantitative and Qualitative Risk Analysis and Risk Response Planning
What comes before:

Create Process Improvement Plan
Finalize "how you will execute and control" the PM Plan
What comes before:

Determine roles and responsibilities
Determine Quality Standards, Processes and Metrics
What comes before:

Risk Identification and Risk Response Planning
Determine Communications Requirements
What comes before:

Estimate Resource Requirements
Create Network Diagram
What comes before:

Create Activity List
Create WBS and WBS dictionary