Project Earned Value Exercise Paper

Great Essays
Project Earned Value Exercise

Project 1
June (Monthly) Performance Data

WBS Work Package
June Budget Cost
June Actual Cost
June Earned Value
1.0
WP 1
$200
$100
$400
2.0
WP 2
1,500
1,800
1,500
3.0
WP 3
1,800
2,100
1,900
4.0
WP 4
500
100
800

Total
$4,000
$4,100
$4,600

Project Number 1 Performance Report (Project-to-Date) As of June 30
WBS
#
WBS Work Package
PV ($)
EV ($)
AC ($)
Cost Variance. ($)
Cost Variance (%)
Schedule Variance ($)
Schedule
Variance (%)
1.0
WP 1
25200
20400
18600
1800
9%
-4800
-19%
2.0
WP 2
6500
6500
6600
-100
-2%
0
0%
3.0
WP 3
9800
3900
5300
-1400
-36%
-5900
-60%
4.0
WP 4
2500
1800
1600
200
11%
-700
-28%

Total Project
44,000
32,600
32,100
500
2%
-11400
-26%

Performance Report (Project-to-Date) As
…show more content…
Work Package 3 has just commenced. So far, Work Package 4 has not started at all. Finish the following earned value report table. The full budget for this project is $53,000. Work projects 1 through 4 are allocated $26,000, $12,000, $10,000 and $5,000 respectively.

Performance Report (Project-to-Date)
As of June 30

WBS Element
PV ($)
EV ($)
AC ($)
Cost Var. ($)
Cost Var. (%)
Schedule Var. ($)
Schedule
Var. (%)
1.0
WP 1
$26,000
$26000
$25,500
$500
2%
$0
0%
2.0
WP 2
$9,000
6000
5,400
600
10%
-3000
-33%
3.0
WP 3
$4,800
5000
4,100
900
18%
200
4%
4.0
WP 4
$0
0
0
0
0%
0
0%

Total
$39,800
$37,000
$35,000
$2,000
5%
-$2,800
-7%

Because this project is comprised of only four components, the results are inconclusive. This is because of the distortions that come about when the earned value allocated to distinct tasks formulae are considerable and do not cancel out one another. In this case, the earned value requires accrual to distinct (discrete) tasks, since this makes it easier for the client to assess this project satisfactorily. Thus, this explains why the client is bound to attempt to negotiate the accrual based earned value formula, as opposed to the allocated based earn value

Related Documents

  • Improved Essays

    Elisha, for the month of April you scored 7.6 points per hour. Your current yearly average is 7.3 points per hour. The team average for the month of April was 9.2 points per hour and the department average for the same month was 9.2 points per hour. Elisha, you continue to perform well below the department expectations in productivity month-over-month. As stated before this cannot continue.…

    • 407 Words
    • 2 Pages
    Improved Essays
  • Great Essays

    (Note: Providing just numbers will receive only partial credit.) Project A: The budgeted cost of work performed is $72,000, and the actual cost of work performed is $75,000. The budgeted cost of work scheduled is $73,000. (15 points) Project B: The budgeted cost of work performed is $48,000, and the actual cost of work performed is $100,000. The budgeted cost of work scheduled is $122,000.…

    • 961 Words
    • 4 Pages
    Great Essays
  • Decent Essays

    Is3350 Unit 3 Project

    • 432 Words
    • 2 Pages

    There are more than 100 activities listed in you WBS, and the high level deliverables nearly mention all of the project objectives. The environment impact report is very appreciated, as the project sponsor asks you to make a environment-friendly project. 2. What questions do you have about what the team did and why they did it? I am still confused about that how the lobor cost of the project team and the design team could be $17 per hour and $25 per hour?…

    • 432 Words
    • 2 Pages
    Decent Essays
  • Improved Essays

    1. Organizations have many different new opportunities, issues/problems, or new technological needs to be filled and will then initiate a project to solve, or take advantage of the case. For example, is a company needed to increase moral of work personnel, they could assign a task force to accomplish this project to increase moral. 2. An organizational information system can allow a company to accomplish any goals or checklists they may hold and therefore relates to the company strategy.…

    • 806 Words
    • 4 Pages
    Improved Essays
  • Improved Essays

    Eco 372 Week 1 Assignment

    • 475 Words
    • 2 Pages

    Part 1: College is a great place to meet new people of all different cultures. In fact, one experience I had with an individual of another culture took place at college. During my freshman year at Towson University, I enrolled in a Biology lecture with over 150 students and I happened to sit next to, Bella, a girl who was from Italy. As the semester went on, I got to know her better and learned that she was studying abroad for a semester. Even though she spoke English fluently, she had a very strong accent and I later learned that her native language was Italian.…

    • 475 Words
    • 2 Pages
    Improved Essays
  • Improved Essays

    Mcclure Case Summary

    • 524 Words
    • 3 Pages

    The company’s President prepared three bid worksheets to determine the bid amount for this project. The error occurred on the worksheet formulas by not successfully transferring the correct amount to the bid sheet. This error lowered his bid by $16,530 due to this error. His bid was the lowest of 8 bids. The Department of the Navy noticed the disparity in his bid between McClure for $145,000 and the Government $282,869.…

    • 524 Words
    • 3 Pages
    Improved Essays
  • Superior Essays

    Project Strategy and Planning When planning for the Alliance Prototype Project, we took a very structured approach. Group members were assigned formal roles, which were then used to delegate portions of the planning document. Each section of the planning document was completed individually, but was revised at a follow up meeting where the group discussed their rationale behind each of their decisions. When formulating the scope statement, our Quality Manager focused on key deliverables and defined constraints, synthesizing the available information into one cohesive statement. Our Risk Manager brainstormed a list of all possible risks when executing the simulation, assigned probability and cost impacts to each, and then decided whether to accept…

    • 1288 Words
    • 5 Pages
    Superior Essays
  • Improved Essays

    According to Jane McCarthy graduate of University of Nevada she states, “Indigenous peoples are spoken for, not spoken with, in regard to their dreams for the education of their children” (p. 123). Jane McCarthy and Helene Johnson tell about their experiences as an outside teacher teaching on the Navajo Nation. The schools on native nations need to ask what the outstanding educational pedagogies are for the native students and how to implement those practices into the classroom instruction. The Accelerated School Project makes changes to the school curriculum, instruction, and organization which the Navajo Nation School didn’t do so well due to the disconnection with mainstream schools. The Native communities need to come together as a culture…

    • 1062 Words
    • 4 Pages
    Improved Essays
  • Improved Essays

    Our Honors in Action Project was a team effort from day one. Beginning at officer training, we sat down as a team to brainstorm ideas. After a brief debate session, we chose to focus on transgender transition surgery within theme seven: Health and Medicine as Frontiers and developed three questions to guide our research. We also decided on a common reader titled “Trans Bodies, Trans Selves: A Resource for the Transgender Community.” We connected with multiple transgender organizations for information, support, and further understanding of the transgender community.…

    • 405 Words
    • 2 Pages
    Improved Essays
  • Superior Essays

    Criteria Should Zachary use to evaluate the projects Zachary, civil engineering student, has three different projects to be executed. First is related with the improvement in the highway in front of Big John’s supermarket, second is related to repair of Elk Mountain road and third one is repair of bridge over Crockett Creek. However, due to the lack of proper resources, Zachary has to made choice regarding the priority of the projects. In this regard, he has to evaluate all the projects available on the basis of some criteria (Case Study: Transportation Improvement). Some of the crucial criteria that Zachary should use to evaluate the projects can be listed as below: 1.…

    • 1560 Words
    • 7 Pages
    Superior Essays
  • Improved Essays

    Furthermore, by sponsoring the program, Pacific Grove will have a positive NPV with an IRR of 41.28% (Exhibit 3). The initial investment to sponsor the program will be $1,440,000 and other maintenance expenses in future years. However, by using the lowest WACC of 10%, the project produces an NPV of $3,278,174, which makes it profitable. Also, higher WACC's of 20% and 30% produce positive NPV and increase cash flows for Pacific Grove (Exhibit…

    • 1379 Words
    • 6 Pages
    Improved Essays
  • Great Essays

    Project Evaluation Essay

    • 4000 Words
    • 16 Pages

    In project evaluation I have evaluated the entire project that we have done such as finding the results and solution, what can be improved if we face the similar problem in future, what are the key aspects to identify the problem and what all process we have used to complete case study as well as what targets we have set which will help to nail down solution, therefore individual critical review will help us to understand the each roles played by team members and how the team meetings were conducted which results in completion of project also what input we got from the team which will give good output. Background As a group we have done project on Banana NZ it is a Korean manufacturing company which produces computer accessories for business…

    • 4000 Words
    • 16 Pages
    Great Essays
  • Improved Essays

    A. Suppose the company is considering a potential investment project to add to its portfolio. Calculate the following items: Before Home Depot calculates the net present value (NPV), internal rate of return (IRR), terminal value (TV), and modified internal rate of return (MIRR) of its newest potential investment project, the company must first calculate its free cash flows. The calculation begins by subtracting the operating costs and the 20% depreciation expenses from the cash flows derived from sales revenues. Next, the income tax (35%) is then subtracted from the resulting operating income to arrive at the company’s after-tax earnings before income tax. The final step is for Home Depot to add back the depreciation to the after-tax…

    • 1739 Words
    • 7 Pages
    Improved Essays
  • Improved Essays

    2. What information did the vice president fail to analyze? The vice president (VP) fails to analyze the overrun properly. The predictable overrun should be (81+55+73+70)/ (74+52+68+60)*2.66-2.66=$272,283, which is 10.24% of the overall budget, as well as the schedule.…

    • 1080 Words
    • 4 Pages
    Improved Essays
  • Improved Essays

    I think the assessments were somewhat accurate. For the values inventory, it helped me understand my values. Off the top of my head it 's not likely that I think about specific things like what I believe in. in truth it actually takes time to stop and pause and think, I strongly value family. The values assessment helped to get a better understanding of myself which is weird.…

    • 1097 Words
    • 4 Pages
    Improved Essays