How is ACWP defined? |
-actual cost of work accomplished |
|
How is cost variance defined? |
-BCWP - ACWP = CV |
|
How is Scheduled Variance defined? |
-BCWS - BCWP = SV |
|
How is the cost performance index calculated? |
-BCWP/ACWP |
|
How is the schedule performance index calculated? |
-BCWP/BCWS |
|
How is the estimate at completion calculated? |
-actuals to date + remaining work/efficiency factor |
|
List the efficiency factors: |
-Cumulative CPI: Tends to be optimistic - Composite CPI: Tends to be pessimistic - Three month CPI: Shows the most current cost performance -six month CPI: Shows the most accurate Weighted CPI: Weighs cost more than schedule |
|
What does the integrated program management report DID provide? |
- combines the Contract PerformanceReport (CPR) and Integrated Master Schedule (IMS) -into a singleintegrated report to be consistent with good, disciplined programmanagement |
|
What is EVM? |
-An integrated process in the management and oversight of acquisition programs -A management approach to ensure the total integration of cost, schedule and work scope aspects of the program |
|
What EVM metric measures schedule? What are some of the examples of the events? |
-BCWS -Program reviews, critical paths, scheduled simulations |
|
What EVM metric measures performance? What are some examples of its events? |
-BCWP -Tests, TMP, simulations, design reviews, system engineering |
|
What EVM metric measure cost? What are some examples of its events? |
-EAC, BAC, ACWP - Cost estimates, CFSR, CCDR, WBS |
|
Budgeted Cost of Work Scheduled is defined as... |
-Represents the value of work planned to be accomplished |
|
Budgeted cost of work performed? |
-represents the value of work accomplished in relation to the PMB |
|
Actual cost of work performed? |
-represents the actual cost of work accomplished |