10 Cards in this Set
- Front
- Back
Which of the following are risk responses? (Select TWO) |
C. Acceptance |
|
When handling multiple changes on a project, which of the following would be the BEST format in which to inform the team? |
A. Follow the communication plan |
|
While developing a project schedule, which of the following are purposes of a milestone? (Select TWO) |
B. Milestones are considered a placeholder in time for a major event |
|
Which of the following is a formula for estimating? |
D. (Optimistic + (4 x Most Likely) + Pessimistic) / 6
|
|
Which of the following network diagram methods uses arrows to represent activities, but is limited because it can only represent Finish-to-Start dependencies? |
A. Arrow Diagramming Method (ADM) |
|
Which of the following is the key characteristic of the WBS? |
A. It represents the entire scope of work for the project |
|
Which of the following tools is used for determining activity schedules based on optimistic, most likely and pessimistic estimates? |
B. PERT |
|
In which of the following team development stages would the project manager MOST likely determine the structure of the project team? |
C. Forming |
|
Which of the following would be important to remember when scheduling a teleconference for a project team? |
D. Considering time zone that meets business hours for whole team
|
|
Which of the following is the condition in which the team just cannot finish the last piece of work and cannot complete the project? |
C. The 95 percent phenomenon |