A project can best be defined as:
|
A temporary undertaking of inter-related activities having a definable time frame and objectives that creates a unique product of service.
|
|
structured project management provides organizations with a methodology to:
|
Become more efficient and effective in accomplishing goals that cannot be handled well by the traditional functional organizational structures.
|
|
The four target core functions (key project performance) categories are:
|
time, cost, scope, and quality
|
|
the most common non-behavioral reason for projects being completed late and over budget is:
|
Ill defined requirements
|
|
a good definition of a successful project is getting the project completed:
|
within time, cost, performance requirements(scope)/quality, and accepted by the user.
|
|
a project is:
|
a series of tasks that have a specific objective, defined start and end dates, are interrelated, and may or may not consume resources.
|
|
the core function of a project manager is:
|
integration
|
|
the greater the need for project integration, the greater the project manager's ___________skills need to be.
|
communication
|
|
another name for key project processes is:
|
process groups
|
|
the process groups, (or key project processes) are: ---there's 5
|
initiation, planning, execution, monitoring and control, closing
|
|
the most significant problem area in project integration management is:
|
behavioral problems
|
|
A program is:
|
a group of related projects that are managed in a coordinated way.
|
|
A project is:
|
a coordinated undertaking of interrelated activities directed toward a specific goal that has a finite period of performance.
|
|
The traditional definition of a program is:
|
A group of projects managed in a coordinated way to obtain benefits not available from managing them individually.
|
|
project integration management describes the processes which are:
|
required to ensure that the various elements of the project are properly coordinated.
|
|
A project management office is:
|
a formalized structure directed toward the support of the project.
|
|
The core project functions must be considered in what order?
|
scope, quality, time, cost
|
|
Which single word best describes scope:
|
what
|
|
Which is the most important "toll gate" on a project, (between which phases)?
|
the one between planning and execution
|
|
which formalities are often "skipped" in?
|
closing and planning.
|
|
the potential for adding value is greatest during which stages?
|
intitiation and planning
|
|
cost of correcting errors is highest in what stage?
|
execution
|
|
classical view:
|
one best way, mechanistic, quantitative, established set of formal principles
|
|
behavioral view:
|
focuses on the human and behavioral aspects that are inherent to projects
|
|
systems view:
|
acknowledges the complexity and causal relationships inherent in projects
|
|
contingency approach/view
|
integrates the classical, behavioral and systems views of project management into a single perspective.
|
|
the project schedule is developed during what phase?
|
planning
|
|
the most important reason that project management is more important now than 30 years ago
|
the rate of change has accelerated
|
|
building a new mcdonalds is:
|
a project
|
|
the s curve of project expenditures describes what
|
the fact that project spending is highest during execution
|
|
the key difference between a project and a program is
|
a project has a clear endpoint, a program may not.
|
|
good project objectives must be:
|
realistic, attainable, specific
|
|
what is not included in the project charter:
|
activity duration estimates
|
|
Who issues the project charter?
|
a senior official in the managing organization
|
|
The best method to achieve a realistic project plan is:
|
Project manager creates the project plan based on input from the team
|
|
the project charter can be changed by
|
sponsor or senior manager
|
|
project charter:
|
a general narrative description of a project's purpose, together with a narrative statement of management authorization
|
|
key reason for including a statement of key assumptions/concerns/constraints in the project charter is:
|
it may help the team identify activities that may otherwise be omitted
|
|
inputs to the initiation of a project include (these are things that will spark the need for a project in the first place):
|
product description
strategic plan historical information selection criteria |
|
project charter is effectively an agreement between the:
|
project manager and the project sponsor
|
|
in order to ensure buy in and comprehension of stakeholders project objectives must:
|
be realistic and attainable
|
|
What one word explains the statement of project objectives in the project charter
|
why
|
|
SMART
|
specific, measurable, agreed-upon/assignable, realistic/relavant, and time-oriented
|
|
triple constraint
|
time, cost, quality
|
|
What one word best describes the statement of deliverables in the project charter?
|
what
|
|
another key reason for including the assumptions, constraints and concerns section of the project charter:
|
helps build team member commitment
|
|
What best describes the implementation of several mini projects rather than a large scale project
|
"rapid results initiatives"
|
|
The project sponsors role is:
|
helping to prevent unecessary changes to the project objectives
|
|
in terms of project planning, the project constraints should be addressed in the following order:
|
quality, time, cost
because you define the quality and that dictates to time and cost |
|
attribution problems in relative long term objectives to project results are best described as
|
problems on intervening variables that impact the long term measures that are not under the control of the project team
|
|
scope verification is associated with which phase?
|
monitoring and control
|
|
WBS represents
|
all the work content in the project
|
|
WBS is used for:
|
The basis for organizing and defining the total scope of the project
|
|
Why should the WBS be used on a project?
|
To prevent work from slipping through the cracks
|
|
The process of creating the WBS creates what in the team?
|
Team buy in.
|
|
WBS dictionary
|
defines the work that is included in each work package
|
|
How detailed should the WBS be?
|
the scope of the work should be as detailed as necessary for the type of project
|
|
What isn't used in creating the WBS?
|
organizational structure of the performing organization
|
|
Proper project scope definition will result in:
|
improved accuracy of cost and duration estimates
|
|
The step immediately prior to generating the WBS
|
Write the project scope statement
|
|
How does scope verification differ from scope definition?
|
Scope verification is accomplished after the project work tasks are complete, scope definition is primarily done before the tasks are started
|
|
rolling wave refers to:
|
THE PROGRESSIVE ELABORATION OF DETAILING OF THE PLAN THROUGHOUT THE PROJECT PHASES
|
|
The first level of the WBS is organized by:
|
Project deliverables or by project phases
|
|
progressive elaboration in scope planning is best described as (aka rolling wave)
|
start scope planning with a broad, general picture of the project then progressively add details
|
|
100% rule
|
In WBS: 100% of the work content in a WBS work package should be described by the content of the work packages below it.
|
|
order of key project actions/documents
|
Project charter
requirements documentation project scope statement WBS WBS dictionary |
|
the collect requirements process results in:
|
the Requirements traceability matrix
|
|
What is the RTM:
|
Requirements traceability matrix: is a table linking requirements to their origin and also linking requirements through the project life cycle (ex through testing), it guarantees a match between requirements and the test for the requirement.
|
|
project scope baseline is composed of which documents:
|
Project scope statement, WBS, WBS dictionary
|
|
Who should develop the project scope baseline?
|
Project team
|
|
8/80 rule
|
Work packages should contain between 8 and 80 hours of work
|
|
gold plating is:
|
exceeding exectation by giving the customer more than what was agreed upon
|
|
rolling wave planning:
|
near term work is planned in detail and future work is planned at a higher WBS
|
|
technical basis for sequential precedence relationships:
|
nature of the work itself demands that activities be undertaken in a particular sequence
|
|
Policy/preferential/dicretionary/soft logic basis sequential precedence relationships:
|
professional practices or standards of how the work should be done to maximize efficiency
|
|
restricted resource basis for sequential precedence relationships:
|
We can only undertake certain work at a certain time because of physical SPACE limitations
|
|
external basis for sequential precedence relationships:
|
government or customer requirements that force a certain order
|
|
Abbreviation for precedence diagram:
|
PDB
|
|
CPM network diagram stands for:
|
Critical path method network diagram
|
|
Building the network diagram is part of:
|
Project time management
|
|
order of project time management processes:
|
define activities, sequence activities, estimate resources, estimate activity duration, develop schedule
|
|
an unintended break in a network path usually caused by missing activities or missing logical relationships.
|
hanging node
|