16 Cards in this Set

  • Front
  • Back

UCA Definition

Any contract action for which the terms, specs or price are not agreed upon before performance is begun under the action

UCA Advantages

Fulfills am immediate need

UCA disadvantages

Doubles workload


No incentive to control cost

8 steps of UCA process

Assess the scope of the requirement


Formulate requirements package


Request NTE


Receive and evaluate NTE


Reach agreement with ktr on requirements, NTE and Definitization schedule


Obtain UCA funding


Obtain authorization to issue UCA


Issue UCA to include ktr’s signature

Who approved UCAs?

HCA (delegable to the SCO?)

7 items in UCA approval package

NTE amount


Need for the UCA


Explain the effort to not use UCAs for current and future efforts


Obligation amount


Definitization schedule


Estimated amount that will be completed before Definitization


Coordination and approval

UCA Elements - 10

Be as complete and definite as possible


Include NTE price w/CLIN structure


Definitization schedule


Limitation of Government Liability and Contract Definitization Clause


SOW


T&C


POP


Ktr signature


Determine amount to obligate


Funds shall be committed for the full amount of the UCA NTE

DoD Policy that UCAs shall

Be used only when the negotiation of a definitive contract action is not possible in sufficient time to meet government requirements


The government interest demands that the ktr be given a binding commitment so that performance can begin immediately (i.e. loss of life)


-PMs should provide rationale


Be as complete and definite as possible with the circumstances

UCA Clause I

Limitation of Gov’t Liability 52.216-24


Ktr not authorized to incur cost >50% prior to qualified proposal/75% after


Max amount the gov’t is liable for if terminated is the NTE

UCA Clause II

Contract Definitization 52.216-25


The ktr agrees to submit a proposal, pricing data, or certified cost or pricing data


Definitization schedule


And it authorizes the CO w/HCA approval to determine price if no agreement can be reached

How is the amount obligated figured?

CO shall assess the ktr proposal for undefinitized period


Shall obligate finds only in amount consistent with spend plan


No motivation to control cost

How do you commit funds for UCAs?

Full amount of the UCA NTE


Incremental funding, commit total for current FY, and budget for the remaining

What needs to be requested from HCA?

Beginning performance before Definitization, includes the adverse impact on the results of delay


Including requirements for non-urgent spare parts. The inclusion should show consistence with good business practices and best interest of Gov’t


Modify scope of the UCA after performance begins

What is the Definitization schedule?

Earlier of the two


- 180 days after UCA issuance or receipt of qualifying proposal


- the date the amount obligated is equal to or greater than 50%

What happens if exceeds 180 days?

SCO needs to brief HAF Staff (SAF/AQC)

7 Points of Definitization

UCAs that fall 14 days behind schedule SCO must provide HCA a status report of remedial actions


Gov’t cannot obligate more than 50% of the NTE before Definitization


If not receiving a qualifying proposal in a timely manner the CO may suspend or reduce payment


Profit shall reflect risk for remaining amount


Cannot negotiate above NTE


CO uses funding that is current and available


If parties can’t agree then CO has unilateral right to decide price with HCA approval